DMIS S I R Entry

Dimensional Measuring Interface Standard
Standard Improvement Request

SIR No.
97-70
DMIS Release
3.0
SIR Type
Other
Severity
Documentation Deficiency
Status
Resolved
Date Submitted
August 18 1997
Date Validated
August 18 1997
Date In Process

Date Referred

Date Vote Pending

Date Closed
August 20 1998
Action
Clarifications
Submitted By
Thomas Kramer
NIST
Room B-124, Bldg. 220
Gaithersburg MD 20899
USA
Phone: (301)975-3518
Fax: (301)990-9866
kramer@cme.nist.gov

Problem Topic
DATSET: Initial CS clarification

Problem Description
Note: This is the first of four SIRs relating to DATSET on pages 17 to 19 (section 3.5). Last week I sent in four SIRs concerning DATSET on pages 113 and 114.

This section does not say what coordinate system is in effect at the beginning of a program.

This raises several questions. Is there a default system in effect? If so, presumably it is MCS. If there is no default system in effect, if a feature is defined, how can it be located? Is it required that a coordinate system be specified before any features can be defined?

References
None

Related SIRs
None

Suggested Resolution
My preferred resolution is to rethink and rewrite DATSET.

To fix only this specific problem, add a sentence describing how it is determined what coordinate system is in effect (if any) when a program starts. If no coordinate system is in effect at the beginning of a program, add a second sentence saying a coordinate system must be defined before any features are defined.

Support Documentation
None


Resolution

Warning!!

The following statement is only a resolution to a Standard Improvement Request (SIR) and is NOT part of the current DMIS standard, nor is it guaranteed to become part of the next revision of the DMIS standard even if voted and accepted by the DMIS National Standards Committee. This resolution is tentative because it may not be incorporated into the next version of the standard, it could be changed prior to the next release, or it could be changed as the result of the "public review and comment" period required for the next version of the standard. If you choose to use this tentative resolution, you do so at your own risk since at this time it is not part of the DMIS standard.

Resolved per 8/98 DNSC Meeting Oak Ridge, TN.

There are no default settings. See section 3.1.3.5 for clarification.

Attachments
None

Notes

Added by Mike Holloway, hkm@ornl.gov on 7/31/1998

See section 3.1.3.5 for clarification.

Added by Interpretation Subcommittee, hkm@ornl.gov on 8/7/1998

There are no default settings. See section 3.1.3.5 for clarification.

Return to SIR List